×

Erith Contractors Limited, established in 1967 – has been awarded the contract to demolish the iconic Aberthaw Power Station.

With nearly 60 years’ experience in this highly-specialised field, Erith have built a stellar reputation for excellence across safety, responsibility, community engagement and environmental sustainability – with comprehensive services that span demolition, asbestos removal, remediation, earthworks, infrastructure, waste management and haulage divisions.

The Erith team commence operations on February 19th 2024, with a projected completion date of March 2027 – this three-year timeline reflecting the extensive scope of the project, and the meticulous planning and execution required, for a transformation that will help shape the future of sustainable energy and advanced manufacturing, for Cardiff Capital Region and beyond.

Complete commitment to safety and environmental stewardship

“We are pleased to announce that Erith Contractors has been selected as the demolition contractor for the Aberthaw Power Station,” said Christian Cadwallader, Interim Managing Director of CCR Energy, “not least as their proven track record of delivering complex projects with a commitment to safety and environmental stewardship aligns perfectly with our vision for the site’s transformation.”

Safety will be paramount during the demolition process – particularly around the removal of asbestos present within the power station – with Erith implementing stringent safety measures in compliance with Health and Safety Executive (HSE) guidelines and the Control of Asbestos Regulations 2012.

These rigorous and robust measures will ensure the safe removal of asbestos prior to demolition, safeguarding both workers and the surrounding community – with Erith emphasising: “We are honoured to have been entrusted with this significant project – and our team is fully prepared to execute the demolition works with the utmost professionalism, prioritising safety, environmental sustainability, and community engagement throughout the process.”

Transparently and proactively engaging with the community

With community and collaboration at the heart of CCR Energy’s vision, residents living near the site can expect both transparent and proactive communication from Erith.

The company has established real-time monitoring stations to track noise, dust, and vibration levels, enabling prompt action in the event of any concerns – as well as making significant enhancements to site security, including fence line improvements and CCTV, to build a safe and secure environment.

“We understand that demolition works may raise concerns among residents, and we are fully committed to addressing these concerns proactively,” assures Erith “which is why we believe that open communication with the community is essential, and we encourage residents to reach out with any questions or feedback they may have.”